PUBLIC NOTICE: FFY 26-30 TIP Amendment 1

Eleven (11) State Funded Transit Projects – New Projects

The Greater Buffalo-Niagara Regional Transportation Council (GBNRTC), the Metropolitan Planning Organization (MPO) for Erie and Niagara Counties, is proposing to amend the 2026-2030 Transportation Improvement Program (TIP) by adding eleven (11) new projects.

1. PIN 5826.44 Lafayette Station Upgrades and Repairs

  • Project will make needed upgrades and repairs to the inbound and outbound Lafayette Street Station roof and related structures.

  • Total Cost: $4.45M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B8 (Reconstruction or renovation of transit buildings and structures)

2. PIN 5826.45 Rail Station Panel Liner Replacements

  • Project will replace life-expired station panel liners at Metro Rail stations

  • Total Cost: $4M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B8 (Reconstruction or renovation of transit buildings and structures)

3. PIN 5826.46 Rail Train Control System Replacement

  • Project will replace the train control system for Metro Rail

  • Total Cost: $4M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B6 (Construction or renovation of power, signal, and communications systems)

4. PIN 5826.47 Rail Enhanced Digital Access Communication Systems

  • Project will replace the radio communication system for NFTA-Metro Rail

  • Total Cost: $5.35M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B6 (Construction or renovation of power, signal, and communications systems)

5. PIN 5826.48 Rail Tunnel Grouting

  • Project will inject fluid-like grout (cement, chemicals) into soil or rock fissures in the NFTA-Metro Rail tunnel to control water, stabilize ground, fill voids, and enhance structural support in the tunnel

  • Total Cost: $1.5M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B9 (Rehabilitation or reconstruction of track structures, track, and track-bed in existing rights-of-way)

6. PIN 5826.49 Rail Subsurface Ventilation Damper Replacements

  • Project will replace life-expired ventilation dampers at all subsurface Metro Rail stations

  • Total Cost: $3M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B8 (Reconstruction or renovation of transit buildings and structures)

7. PIN 5826.50 Rail Tunnel Fiber Optic Installation

  • Project will install fiber optic cables along the NFTA-Metro Rail tunnel

  • Total Cost: $3.7M (100% SFY 25-26 NYSDOT Public Transit State Rail Capital funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B6 (Construction or renovation of power, signal, and communications systems)

8. PIN 5826.51 Bus Garage HVAC Replacement

  • This project will design and replace the Heating Ventilation & Air Conditioning (HVAC) Units in NFTA-Metro’s bus garages

  • Total Cost: $4.55M (100% SFY 25-26 NYSDOT Modernization & Enhancement Program (MEP) funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B8 (Reconstruction or renovation of transit buildings and structures)

9. PIN 5826.52 Bus Garage Fuel Tank Upgrades

  • Project will purchase and install fuel tank upgrades at NFTA bus facilities

  • Total Cost: $1.13M (100% SFY 25-26 NYSDOT Modernization & Enhancement Program (MEP) funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B6 (Construction or renovation of power, signal, and communications systems)

10. PIN 5826.53 Bus Garage Door Replacements

  • Project will remove aging garage doors and replace them with new insulated doors

  • Total Cost: $1.25M (100% SFY 25-26 NYSDOT Modernization & Enhancement Program (MEP) funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B8 (Reconstruction or renovation of transit buildings and structures)

11. PIN 5826.54 Battery Electric Buses (BEB)

  • Project will provide for the purchase of Battery Electric Buses that will replace life and mileage expired vehicles

  • Total Cost: $5.177M (100% SFY 25-26 NYSDOT Accelerated Transit Capital (ATC) funds)

  • Let (Obligation) Date: 3/1/2026

  • Proposed Transportation Conformity Exemption: B10 (Purchase of new buses and rail cars to replace existing vehicles or for minor expansions (< 10%) of the fleet)

Public comments will be received for 30 days from 1/8/26 until Close of Business (COB) on 2/9/26.

Comments may be submitted to GBNRTC via email at staff@gbnrtc.org or by voicemail at 716-856-2026 x300 or by mail at 438 Main St, Suite 503, Buffalo, NY 14202.

Click here to view the full public notice.